Builder’s extras and variations: how to check them before you pay

In Portugal they’re called trabalhos a mais, work in addition. In the UK and Australia, variations. Whatever the name, they are how a €150,000 renovation becomes a €195,000 one, and most owners approve them one at a time without ever seeing the total move. Some extras are fair. The house is old and the walls had a surprise in them. Some are the quote coming home to roost: things that were always going to be needed and were left out to win the job. Here is how we tell them apart on the jobs we oversee.

Mid-renovation and nobody’s checking? The Project Room puts a builder on your side of the table: we check the work before it’s covered up, read every extra against the original quote, and show you what you’ve paid against what’s been built. From €690 + IVA a month.

Why the bill grows

Three reasons, and they overlap.

The first is the building. An 1890s Porto house or a 1960s moradia will hide things. Rotten beam ends behind a plastered wall, a floor slab with no insulation and no damp proof under it, a sewer run that goes under the neighbour’s kitchen. Nobody could have priced those from a viewing. These are real extras and the only question is the price.

The second is the quote. Portuguese renovation quotes are often short on detail and long on “a definir”. If the electrics line says “instalação elétrica nova” and nothing else, the consumer unit, the earth, the CERTIEL certificate and the sockets you actually wanted all arrive later as extras. That’s not the house surprising anyone. That’s a quote written to be the lowest on the day. We cover what a thin quote leaves out in what a builder’s quote leaves out.

The third is you. Owners change their minds. The kitchen moves, the bathroom gains a niche, the window gets bigger. Each one is legitimate work and each one should be priced before it happens, not discovered on the invoice.

What a proper variation looks like

On a job that’s being run properly, an extra arrives as a short written note before the work is done. It has:

If that sounds like a lot of paperwork for €600 of extra plumbing, it is five minutes’ work for a builder who’s organised. Builders who say they don’t have time for it generally don’t have time to keep track of your money either.

Old electrical distribution board in an older Porto house, the kind that becomes an extra once the walls are open
A board like this was always going to be replaced. If it wasn’t in the quote, the extra isn’t a surprise. It’s the quote catching up.

The checks we run on every extra

Was it in the original scope? We go back to the quote and the drawings. If the work was described there, even loosely, it isn’t an extra. A quote that says “new bathroom, complete” includes the waterproofing. A builder who then charges for tanking is charging twice.

Could it have been seen at quoting? A consumer unit from 1975 is visible at the first visit. Rot inside a boxed-in beam is not. The first should have been priced. The second is a fair extra.

Is the price right? We price it ourselves from the same market the builder buys in. On the Porto jobs we’ve looked at this year, extras came in anywhere from fair to about double what we’d have charged. A new 24-module consumer unit with RCBOs per circuit, fitted and certified, sits around €1,500–2,200 + IVA. Replacing a rotten 4 m floor beam in an old house, €700–1,400 depending on access. If the number is a long way off, we ask for the breakdown.

Is there a cheaper way to the same result? Sometimes the builder’s extra is the Rolls-Royce fix when a sound, simpler one exists. Sometimes it’s the reverse and the cheap fix will be back in two years. We say which.

What does it do to the total? This is the one owners miss. Each extra looks small. Twelve of them at an average of €1,800 is €21,600, and if the contingency was 10% on €150,000 you’ve just spent it all with the plastering still to come.

Want someone reading the builder’s extras before you pay them? That’s what the Project Room does. From €690 + IVA a month.

Three extras we’ve pushed back on this year

What to put in the contract before you start

If you haven’t signed yet, this is the moment. The contract should say that no extra is paid unless it was priced and approved in writing before the work was done. It should name a rate basis for labour and a mark-up on materials, so pricing extras isn’t a negotiation every time. And it should say that stage payments are for stages reached, not dates reached. How to structure that is in how to pay a builder without paying ahead of the work.

If you have signed and none of that is in there, you can still start doing it from today. Most builders accept it once someone on your side asks, and the ones who don’t are telling you something.

Prices are from our own quotes and the jobs we have overseen in 2025 and 2026, ex IVA, Porto area. Other regions and access conditions move them. Treat them as a guide to scale, not a quote.

What the Project Room looks like

One private page on your phone. No app, no login. This is a demonstration job.

Project Room home screen: the stage in progress, the next visit before cover-up, and a variation waiting for the owner's decision
Home. Where the job is this week, and the one thing that needs you.
Project Room progress screen: stages that get covered up, which ones we have photographed and checked, and the stage list
Progress. The stages that disappear behind plaster and tiles, and whether we’ve seen them first.
Project Room money screen: paid to the builder against work we have seen, with a warning when payment is ahead of progress
Money. What you’ve paid next to what we’ve actually seen built. When the first runs ahead of the second, it says so.

A builder on your side of the table.

You keep your builder. We check the work at the stages that disappear behind plaster and tiles, read every variation against the original quote, and keep what you’ve paid lined up against what we’ve actually seen built. All of it on one private page on your phone. From €690 + IVA a month. If the job has already stopped, Build Rescue picks it up: we assess it, put it in writing and find a builder to finish it.

Haven’t bought yet? Pre-purchase inspection from €490 + IVA.

Or message Brad on WhatsApp. Same-day reply.